PROJECT INFORMATION
Works within the scope of contract Asphalt repair and coating
Progress Completed
Contract price USD 89.378.888,00 TL (33.688.473,11 USD)
Employer / Investor Kahramanmaraş metropolitan municipality
Close Summary

Project Information

Within the scope of Kahramanmaraş Metropolitan Municipality road construction work, in all district centers and connection roads within provincial borders earthworks, art structures and superstructure works were completed.

Approximately 800.000 tons of bituminous hot mix production was made and delivered to the employer successfully within 15 months.

Statistics

2.500 m2

Sathi Kaplama

800.000 ton

Sıcak Karışım

1.00.000 ton

Temel-Alttemel

4.500 m3

Beton

1.100.000 m3

Kazı-Dolgu